Check task and Assignment Progress (Workload and Deadlines) (v8.xx)

Check task and Assignment Progress (Workload and Deadlines) (v8.xx)

A project leader will need to track the actual work done on his/her project at any given time. The planned workload can be compared to the actual work performed on tasks/assignments. Most of the tasks and assignments tracking reports are part of the contextual navigation menu [Tasks & Plan] of the "Projects" module. Here are some examples.


To check a task’s workload status, use the report view on task displaying planned, actual, remaining,


re-estimated at completion workload, as workload delta (the difference between planned and re- estimated).



To check a resource assignment’s progress check for instance the view "Assignments" of the contextual navigation menu [Task & Plans-->Assignments] of the "Project" module.



Project status reports also give an overview of task’s status. See below.


To check a project’s workload status on a monthly basis, use the report view on the project overview to display planned, actual, remaining, re-estimated at completion workload.




Note: See the "Project Overview" record description to understand the colour codes.


To check a resource’s workload status, use the report view on assignments displaying planned, actual, remaining, re-estimated at completion workload, as workload delta (the difference between planned and re-estimated).


Visit also the list of Geniusproject built-in reports for more reports on those topics.
    • Related Articles

    • Check Project Status and Progress (v8.xx)

      A project Manager wants to know the status of his(her) project(s). Project managers want to have a clear view of project status, and deadlines? Are they on time? Budget? Any risk or quality problems? What is the project’s trend? Geniusproject ...
    • Tracking Task Costs (v8.xx)

      Geniusproject offers two possible ways to post time so workload costs can be tracked: Using the [Timesheets] module: Users enter their workload details in a timesheet. They user can also propose a new "remaining" time, that must be accepted or ...
    • Check Resource Availability (v8.xx)

      Once your list of resources has been defined, project managers can now begin selecting their project teams. In order to avoid selecting resources that may already be scheduled to work on other projects, that may not have the proper skills or that may ...
    • Resource Availability and Workload (v8.xx)

      Many companies face the challenge of meeting project requirements without overstaffing or under- utilizing resources. Having a solution to plan and manage resource capacity and balance it against work demand is a required component of any project and ...
    • The Workload Chart (v8.xx)

      The Workload chart is a color coded diagram displaying a selected resource’s workload across all projects they are assigned to, including all scheduled unavailabilities. The Workload Chart is a great tool to identify a resource’s allocation across ...