Tracking Task Costs (v8.xx)

Tracking Task Costs (v8.xx)

Geniusproject offers two possible ways to post time so workload costs can be tracked:


  • Using the [Timesheets] module: Users enter their workload details in a timesheet. They user can also propose a new "remaining" time, that must be accepted or rejected by the project manager.

  • Without using the [Timesheets] module: Users can enter their workload details directly in the assignment form. The user can also specify the "remaining". Once the assignment is saved, the task will automatically be updated with the new information and the effective and remaining costs will be calculated automatically in the task, using the resource’s rate.