Check Project Status and Progress (v8.xx)

Check Project Status and Progress (v8.xx)

A project Manager wants to know the status of his(her) project(s). Project managers want to have a clear view of project status, and deadlines? Are they on time? Budget? Any risk or quality problems? What is the project’s trend?


Geniusproject provides a long list of reports helping project managers track projects.


The main project list gives a clear snapshot of a project’s status, including Project Health, deadline, Priority, Progress, start and end dates.



To get more details about project status, go to the contextual navigation "Progress Status" or "Dashboards and charts," in the "Project" module.


  1. Project progress status




The project’s percentage of progress is been calculated by all Tasks. There is no progress, if there is no physical / actual effort.

Note: If you do not have the same settings in project options and all tasks, the project progress won't run.

  1. Project progress per Phase




This chart shows, actual, remaining, planned effort for each project phase.


Calculation for Phase progress:


  1. All Tasks must have a Workload.

  2. You must have saved the initial baseline.

  3. The Project and all tasks must have the same options.

  4. The percentage of progress for labor, based on time spent on tasks belonging to the phase.




  1. Project Monthly Overview, a clear view project status and trend




The view "Project status/Overview by month" based on project overview records, shows project status and progress visual indicators month by month, alowing project managers to see the evolution of the different indicators over periods of time.


Note:  See the "Project Overview" record description to understand the colour codes.

  1. Monthly progress reports


Despite Geniusproject s automatically various indicators, a good project status report requires a project manager’s input.


The 'Progress report' is the document that allows the project leader to give a report on the progress of a project thus far. Beyond the automatic indicators found in the Project overview, these documents allow the Project leader to submit a personal assessment. This is also where he/she is going to give an account of encountered problems, as well as found solutions, if any.


  1. The Progress Report header


Project Name

The project title, in the example above – "ABC Laboratory setup".

Project leader

Name of the project leader. By default, will always be the creator of the new project.




Problems

No: Means the selector "Found problems" is set to "No".

Yes: Means the selector "Found problems" is set to "Yes", and the selector "Solved problems" is set to "Yes".

Yes: Means the selector "Found problems" is set to "Yes", and the selector "Solved problems" is set to "No".

See below the selector’s description.


  1. The General tab



Period

The month for which the report is done. Number from 1 to 12. Mandatory.

The year for which the report is done. Number, four positions (yyyy). Mandatory. The period is then computed with the format mm-yyyy.

Accomplished work

Description

Allows for the description of the part of the project that has already been accomplished.





Accomplished tasks

To select the tasks that has been completed during the period.





Next planned work

Description

Allows for the description of the part of the project that must be accomplished in the next period.

When

Start date of the next planned work.

Task to

accomplish

To indicate the tasks those are to be accomplished in the next period.





Problems


Found problems

Indicate "Yes", if any problems have been encountered during the period. Use the subsequent rich text field to add any comments.


Solved problems

Indicate "Yes", if all the encountered problems have been solved. Use the subsequent rich text field to add any comments.


  1. The KPI tab

This section only appears if the option 'By month' is checked in the field, 'Metric capture mode' of the General setup of the 'Portfolio' database. See KPI module chapter.



  1. The Monthly progress report view

The view "Progress reports" shows a clear view of the project manager’s problems reports on a monthly basis.



  1. Earned Value Tracking


Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of: Scope, Schedule and Costs.


In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.


Earned Value Management (EVM) helps project managers to measure project performance. It is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project forecasting. The project baseline is an essential component of EVM and serves as a reference point for all EVM related activities. EVM provides quantitative data for project decision making.


  1. EVM Measures

EVM consists of the following primary and derived data elements. Each data point value is based on the time or date an EVM measure is performed on the project.


Primary Data Points:


  • Budget At Completion (BAC) - Total cost of the project.

  • Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV) - The amount expressed in Money (or hours) of work to be performed as per the schedule plan.

  • PV = BAC * % of planned work.

  • Budgeted Cost for Work Performed (BCWP) / Earned Value (EV) - The amount expressed in Money (or hours) on the actual worked performed.

  • EV = BAC * % of Actual work.

  • Actual Cost of Work Performed (ACWP) / Actual Cost (AC) - The sum of all costs (in Pounds) actually accrued for a task to date.

For example, say we should have completed $800 of work by today. However, we only completed

$600 worth of work. The BCWP is $600. The BCWS is $800. And if we actually paid $700 then (ACWP) = $700


Derived Data Points - Cost Forecasting:


  • Estimate At Completion (EAC) - The expected TOTAL cost required to finish completed work.

  • EAC = BAC / CPI = AC + ETC = AC + ((BAC - EV) / CPI) (typical case) = AC + (BAC -

  • EV) (atypical case)


Here a typical means it is assumed that similar variances will not occur in the future.


  • Estimate to complete (ETC) -The expected cost required to finish all the REMAINING work.

  • ETC = EAC - AC = (BAC / CPI) - (EV/CPI) = (BAC - EV) / CPI


Derived Data Points - Variances:


  • Cost Variances (CV) - How much under or over budget.

  • CV = EV-AC - NEGATIVE is over budget, POSITIVE is under budget.

  • Schedule Variances (SV) - How much ahead or behind schedule.

  • SV = EV-PV - NEGATIVE is behind schedule, POSITIVE is ahead of schedule.

  • Variance At Completion (VAC) - Variance of TOTAL cost of the work and expected cost. VAC = BAC – EAC.

Performance Indices:


  • Cost Performance Index.

  • CPI = EV / AC - Over (< 1) or under (> 1) budget.

  • Schedule Performance Index.

  • SPI = EV / PV - Ahead (> 1) or behind (< 1) schedule.


The view "Progress status/Earned value" shows earned value indicators by month. This report is based on project’s overview records.



    • Related Articles

    • Check Deliverables Status / Milestone Follow-Up (v8.xx)

      Deliverables are one of the project leader’s best tools to check the project’s progress. They summarize the result of several tasks and give the project leader an immediate view of the project's status. Deliverables can be created directly in the ...
    • Check task and Assignment Progress (Workload and Deadlines) (v8.xx)

      A project leader will need to track the actual work done on his/her project at any given time. The planned workload can be compared to the actual work performed on tasks/assignments. Most of the tasks and assignments tracking reports are part of the ...
    • Workflow Status Definition (v8.xx)

      Once the workflow definition has been created, it is time to list all of the possible statuses a document can pass through when following the workflow. A best practise when going through this exercise is to define all workflow statuses on paper, and ...
    • Project Status Report (v8.xx)

      The document Project status report is an excellent combine of known Project report and Project overview. The report is a predefined form in Genius Project (enable subform to use this document). The document can be created manually with the "Create ...
    • How Project Risk Status Influences Project Status (v8.xx)

      It is important to monitor risk analysis during the project. It is also important to note that the "Risk" section of the Project Overview document keeps track of the risks throughout the life cycle of the project. In the header of the overview is a ...