Check Project Status and Progress (v8.xx)

Check Project Status and Progress (v8.xx)

A project manager wants to know the status of their project(s). Project managers seek a clear view of project status and deadlines Are they on time? On budget? Are there any risks or quality issues? What is the project’s trend?

Cerri Project provides a wide range of reports to help project managers track their project effectively.

The main project list gives a clear snapshot of a project’s status, including Project Health, Deadline, Priority, Progress, Start and End Dates.




To get more details about project status, go to the contextual navigation "Progress Status" or "Dashboards and charts" in the "Project" module.

Project progress status



The project’s percentage of progress is calculated based on all Tasks. If there is no physical or actual effort entered, there will be no progress displayed.

Note: If project options and task settings are not aligned, the project progress will not be calculated properly.


Project progress per Phase






This chart displayes actual, remaining, and planned effort for each project phase.

Calculation prereuisites for Phase progress:
  1. All tasks must have a defined workload.
  2. The initial baseline must be saved.
  3. The project and all tasks must share the same option settings.
  4. The progress percentage for labor is calculated on time spent on tasks within each phase.



Project Monthly Overview - A clear view of project status and trend



The "Project status/Overview by month" views (based on project overview records) shows visual indicators of project status and progress on a month-by-month basis, alowing project managers to monitor trends over time.


Note:  Refer to the "Project Overview" record description to understand the colour codes.


Monthly progress reports


Although Cerri Project automatically calculates various indicators, a solid project status report requires input from the project manager.


The 'Progress report' is the document that allows the project leader to formally report on the current state of the project. Beyond the automatic indicators found in the Project overview, these documents allow the project leader to provide a subjective assessment, descirbe issues encountered, and outline any resolutions.


The Progress Report header



Project Name

The project title, in the example above – "ABC Laboratory setup".

Project leader

Name of the project leader. By default, this will always be the creator of the project.




Problems


  1. No: The "Found problems" selector is set to "No".
  2. Yes: The "Found problems" selector is set to "Yes" and the "Solved problems" selector is set to "Yes".
  3. Yes: The "Found problems" selector is set to "Yes" and the "Solved problems" selector is set to "No".

See below for selector descriptions.


  1. The General tab




Period

The month for which the report is made. Number from 1 to 12. Mandatory.

The year for which the report is made. Four-digit number (yyyy). Mandatory.

The period is then computed in the format mm-yyyy.

Accomplished work

Description

Enter a description of the part of the project that has been accomplished.


Accomplished tasks

Select the tasks that were completed during the period.








Next planned work

Description

Enter a description of the work planned for the next period.

When

Start date of the next planned work.


Task to

accomplish

Indicate the tasks to be completed in the next period.







Problems


Found problems

Select "Yes" if any problems were encountered during the period. Use the associated rich text field to add comments.


Solved problems

Select "Yes" if all encountered problems were solved. Use the associated rich text field to add comments.


  1. The KPI tab

This tab only appears if the option 'By month' is enabled in the 'Metric capture mode' field in the General Setup of the 'Portfolio' database. See the KPI module chapter for more details.



The Monthly progress report view


The "Progress reports" view shows a clear monthly summary of the project manager’s reported issues.



Earned Value Tracking


Earned Value Management (EVM) is a project management technique used to measure project performance and progress by combining scope, schedule, and cost metrics.

It provides accurate forecasts of project performance and is essential for project managers to make data-driven decisions.

EVM compares the planned work with actual work performed and helps control costs and schedules. The project baseline is a key element, serving as the reference for all EVM-related analysis.


EVM Measures

EVM consists of the following primary and derived data points. Each data point value is based on the time or date an EVM measure is performed on the project.


Primary Data Points:


  • Budget At Completion (BAC)

    • Total budget for the project.

  • Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)

    • The value of planned work at a specific time expressed in money or hours.

    • PV = BAC * % of planned work


  • Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)

    • Value of actual worked completed expressed in money or hours.

    • EV = BAC * % of actual work

  • Actual Cost of Work Performed (ACWP) / Actual Cost (AC)

    • Actual costs incurred to date.


Example: If $800 of work was planned but only $600 was completed, and $700 was spent:
  1. BCWP = $600
  2. BCWS = $800
  3. ACWP = $700

Derived Data Points - Cost Forecasting:


  • Estimate At Completion (EAC)

    • Expected total cost to complete project.

    • EAC = BAC / CPI

    • EAC = AC + ETC

    • EAC = AC + ((BAC - EV) / CPI) (typical case)

    • EAC = AC + (BAC - EV) (atypical case)


Typical means it is assumed that similar variances will not occur in the future.


  • Estimate to complete (ETC)

    • Remaining cost to finish the project.

    • ETC = EAC - AC

    • ETC = (BAC / CPI) - (EV/CPI)

    • ETC = (BAC - EV) / CPI


Derived Data Points - Variances:


  • Cost Variance (CV)

    • How much above or under budget.

    • CV = EV-AC

      • NEGATIVE = over budget

      • POSITIVE = under budget.

  • Schedule Variances (SV)

    • How much ahead or behind schedule.

    • SV = EV-PV

      • NEGATIVE = behind schedule

      • POSITIVE = ahead of schedule

  • Variance At Completion (VAC)

    • Variance of total cost of the work and expected cost.

    • VAC = BAC – EAC.

Performance Indices:


  • Cost Performance Index

    • CPI = EV / AC

      • < 1 = over budget

      • > 1 = under budget

  • Schedule Performance Index

    • SPI = EV / PV

      • > 1 = ahead of schedule

      • < 1 = behind schedule.


The "Progress status/Earned value" view shows monthly earned value indicators based on project overview records.




    • Related Articles

    • Check Project Status and Progress (v8.xx)

      A project Manager wants to know the status of his(her) project(s). Project managers want to have a clear view of project status, and deadlines? Are they on time? Budget? Any risk or quality problems? What is the project’s trend? Geniusproject ...
    • Check Deliverables Status / Milestone Follow-Up (v8.xx)

      Deliverables are one of the project leader’s best tools to check the project’s progress. They summarize the result of several tasks and give the project leader an immediate view of the project's status. Deliverables can be created directly in the ...
    • Check Deliverables Status / Milestone Follow-Up (v10.xx)

      Deliverables are one of the project leader’s best tools to check the project’s progress. They summarize the results of several tasks and give the project leader an immediate view of the project's status. Deliverables can be created directly in the ...
    • Check task and Assignment Progress (Workload and Deadlines) (v8.xx)

      A project leader will need to track the actual work done on his/her project at any given time. The planned workload can be compared to the actual work performed on tasks/assignments. Most of the tasks and assignments tracking reports are part of the ...
    • Check Task and Assignment Progress (Workload and Deadlines) (v10.xx)

      A project leader needs to monitor actual work done on projects in real-time. Comparisons can be made between the planned workload and actual work performed on tasks and assignments. The [Tasks & Plan] section of the "Projects" module contains most of ...