Replace a Resource (v10.xx)

Replace a Resource (v10.xx)


This function is used to manage situations where a resource must be replaced with another in a specific database.

  1. Edit the relevant 'Resource' document.
  2. Click on the menu [Actions > Replace the existing resource].


A dialog box will appear, allowing you to select the database where the resource should be replaced and the resource to replace it with. See the table below for details.





Resource to replace

The name of the database in which the resource will be replaced. Single-selection field. Mandatory.

Within the database

The resource that will be replaced. Retrieved from the resource document. Not editable.

Replace with

The list of available resources defined in the 'Resources' database.


  1. Click the [Update] button.
  2. The resource is replaced in the selected database. If the database is a 'Projects' database, the project plan (Gantt chart) is also updated accordingly.


    • Related Articles

    • Replace a Resource (v8.xx)

      This function is used to manage the situation when a resource must be replaced with another in one specific databases. Edit the concerned 'Resource' document. Click on the menu [Actions > Replace the existing resource]. In the dialog box, select the ...
    • Replace a Resource (v10.xx)

      To replace a project team member, ensure that the replacement resource has already been added to the project team. The function is useful when a planned resource needs to be changed during project planning phase (stand-by). Edit the Project ...
    • Action Menu (v8.xx)

      Menu Action Description Shortcut Rea d mod e Edit mod e Sh ort Act ion Me nu General Menu P P P Save Without closing: Saves the current version of the plan. In order to propagate all the changes in all records of the project, the plan is briefly ...
    • Action Menu (v10.xx)

      Menu Action Description Shortcut Read mode Edit mode Short Action Menu General Menu Save Saves the current version of the plan without closing it. Changes in all records of the project are propagated by briefly closing and reopening the plan in edit ...
    • Replacing a Resource (v8.xx)

      To replace a project team member you must first make sure that the replacement resource has already been added to the project team. Next: Click on the "Replace resource" icon on the toolbar In the "Resource replacement" dialog box that opens, select ...