Managing Multiple Types of Deliverables (v8.xx)

Managing Multiple Types of Deliverables (v8.xx)

As mentioned several times above, Geniusproject allows users to convert a deliverable into any type of generic document, cost document or billing milestone. As a result, project deliverables can all be modeled differently. For example, if in one phase there is a "market study" deliverable, and in another phase there is a "pre-engineering study" deliverable, they will not have the same format, and certainly not the same revision and approval cycle. In the context of Stage Gate, Geniusproject deliverables "Gate" (Gate review), will have a specific format (score card), and a specific workflow.


Within the Gantt (Genius Planner), deliverables can only be created as the standard deliverable type. However, it is possible to define other types for deliverables that are created manually outside of the Gantt. (See "Creating a deliverable")


It is also possible to transform any deliverable in its standard deliverable format into any other


supported type. This operation is called "Converting a deliverable"


To convert a deliverable:


Open the deliverable in edit mode.

Click "Actions" on the menu action bar and select "Convert into".


A dialog box will open.

Select the desired target document type.

If the desired type is not a cost document, you can also specify which document template to use.



If the document type is "Cost", you will be able to choose a cost type but not a template. If the document type is not a cost, you will be able to select a template and will not need or be able to select a cost type.

Click "OK" to validate.


The deliverable will automatically be converted into the selected document type. However the section on delivery dates and validations for the standard deliverable are automatically maintained.


  1. Deleting a deliverable


There are three possible ways to delete a deliverable:


From the Genius Planner if it exists in the Gantt.

Directly from the deliverable. Click "Delete" on the menu action bar.

From a view. Select the deliverable(s) to be deleted from the view and lick "Delete" on the menu action bar for the view.



    • Related Articles

    • Deliverables, Milestones (v8.xx)

      The deliverable generally marks the end of a project phase and allows for the approval of the project's key elements. The deliverable can have a material existence (file) or not (meeting), but it is a mandatory checkpoint which requires an approval ...
    • Resource Types (v10.xx) [TR]

      The Resources tab provides access to the various types of resources that exist in the database. Menu Use Resources Lists all of the existing human resources in the database Generic resources Lists all of the existing generic resources in the database ...
    • Document Types Setup (v8.xx)

      Once the list of document types is added to the keywords & labels document, an entry for each type is added to the ‘Document types’ section. All of the Geniusproject standard documents will appear in the list, as well as the types added from the ...
    • Managing Documents in Genius Project (v8.xx)

      Running a project generates a lot of information and documents of all types. It is therefore necessary to have tools available to standardize, classify, list, publish and distribute this information. All of these documents are too often classified in ...
    • Creating Activities – Phases, Tasks & Deliverables (v8.xx)

      An item in Geniusproject can either become a phase, a task or a deliverable. To create and schedule tasks and deliverables in the Gantt chart, click on the item in the table that you would like the new item to be after, and click on the "Insert task" ...