To plan a project template is essentially the same as planning a standard project, with the following exceptions:
The author of the plan (Gantt) should be the 'Project Leader' generic resource. This is because, when the plan is synchronized and tasks are generated, the 'Requester' of those tasks is by default the author of the plan. Defining the author of the plan as a 'Generic Resource' ensures that the Requester of the tasks will be replaced by the actual project leader when the 'Replace the generic resources' option is used.
Resources used in the plan should also be generic resources. Assigning a 'generic' resource follows the same process as assigning a 'named' resource.
It is not mandatory to synchronize the plan of a template. However, it is necessary to synchronize it when tasks, assignments, or deliverables contain information not derived from the plan and need manual updates. Examples include: