Display Critical Path (v8.xx)

Display Critical Path (v8.xx)

A task is potentially critical if the interval between itself and the subsequent linked task is null. It becomes critical when it cannot be delayed without delaying the whole project. Therefore, any task with a planned end date equal to the end date of the project is critical.


The critical path is then a sequence of linked tasks whose intervals are zero. Clicking on the icon in the toolbar will automatically highlight in red all tasks and milestones part of the critical

path.