Display Critical Path (v8.xx)
A task is potentially critical if the interval between itself and the subsequent linked task is null. It becomes critical when it cannot be delayed without delaying the whole project. Therefore, any task with a planned end date equal to the end date of the project is critical.
The critical path is then a sequence of linked tasks whose intervals are zero. Clicking on the icon in the toolbar will automatically highlight in red all tasks and milestones part of the critical
path.
Related Articles
Action Menu (v8.xx)
Menu Action Description Shortcut Rea d mod e Edit mod e Sh ort Act ion Me nu General Menu P P P Save Without closing: Saves the current version of the plan. In order to propagate all the changes in all records of the project, the plan is briefly ...
Toolbar (v8.xx)
Toolbar Action Icon Description Shortcut Re ad m od e Ed it m od e Insert Activity Inserts a new task after the last selected item in the Gantt chart. The new task is appended at the end of the item list if no task is selected. It has a default name ...
The Dynamic Gantt Chart (v8.xx)
The Gantt Chart is used to graphically display the project’s timeline including its phases, tasks, milestones and constraints. The dynamic Gantt Chart can be used to scroll forward and back along the project timeline by clicking and holding directly ...
The Organizational Breakdown Structure (OBS) (v.8xx)
It is possible to create an organizational hierarchy for resources broken down by company and departments. Company records are defined in the [Resources] module and all resources attached to it will inherit certain attributes, such as "Rates" for ...
Create Custom Fields (v8.xx)
It is possible to customize Geniusproject with simple setup actions, to add fields and to create reports based on those fields. You need [Admin] access to do this. Custom fields can be defined for any Geniusproject form as well "generic documents." ...