Items Menu |
|
|
|
|
|
Insert Task | Inserts a new task after the last selected item in the Gantt chart. If no item is selected, the task is appended at the end of the list. The task has a default name and duration of 1 day starting from the present date. |
INS |
|
P |
P |
Insert Milestone | Inserts a new milestone after the last selected item in the Gantt chart. If no item is selected, the milestone is appended at the end of the list.
|
ALT-INS |
|
P |
P |
Copy Items | Copies selected items to the clipboard. Assignments are copied without current progress. Constraints are also copied, if they exist. The clipboard contents are not readable outside the Cerri Planner. |
CTRL-C |
|
P |
P |
Paste Items | Pastes items from the clipboard after the last selected task in the Gantt chart. If no task is selected, the pasted items are appended at the end of the list . |
CTRL-V |
|
P |
P |
Delete Items | Deletes the selected items in the Gantt chart. Confirmation from the user is required before the operation is performed. |
DEL |
|
P |
P |
Item Properties | Opens the Item Properties Window to the "General" section. | CTRL-I | P | P | P |
Phases Menu |
|
|
| P P |
Indent Item | Indents selected tasks to a lower hierarchy level. | CTRL- RIGHT |
| P | P |
Outdent Item | Moves selected tasks to a higher hierarchy level. | CTRL-LEFT |
| P | P |
Items Movement Menu |
Move Item Up | Moves the selected task upwards. The hierarchy level does not change. | CTRL-UP |
| P |
|
Move Item Down | Moves the selected task downwards. The hierarchy level does not change. | CTRL- DOWN |
| P |
|
Timeshift Items | Shifts the selected tasks, milestones, and phases to a new date specified by the user, keeping the start date on the same day of the week. |
SHIFT-T |
|
P |
P |
Links Menu |
| P | P P |
Link Selected items | Links the selected items. | CTRL-L |
| P | P |
Create Link | Creates a dependency between two items. When using this action, the cursor changes to a cross to select the start and end points of the constraint.
|
CTRL-INS |
|
P |
P |
Delete Link | Deletes the selected constraints in the Gantt chart. Confirmation from the user is required before the operation is performed. |
DEL |
|
P |
P |
Link properties | Displays detailed information about the selected link, such as time lag, when two items are linked. |
CTRL-I |
P |
P |
P |